Vermont Yankee Sale

Entergy, NorthStar Reach Settlement Agreement with State of Vermont and Other Parties on Terms for the Approval of the Sale of Vermont Yankee

Entergy Corporation and NorthStar Group Services Inc. announced today they have signed a settlement agreement and Memorandum of Understanding (MOU) with State of Vermont agencies and other interested parties on terms for approval of the proposed sale this year of Entergy Nuclear Vermont Yankee, the entity that owns the Vermont Yankee Nuclear Power Station located in Vernon, Vermont.

The agreement and MOU are significant milestones in the approval of the proposed transaction. If the transaction is approved by the Vermont Public Utility Commission (PUC), it will accelerate the decommissioning of Vermont Yankee by decades and facilitate the eventual economic redevelopment of the site. 

The Vermont agencies signing the agreement, in whole or in part, are: the Department of Public Service (DPS), the Agency of Natural Resources (ANR), the Department of Health, and the Attorney General’s Office.  The following parties have also signed the agreement: the Town of Vernon Planning and Economic Development Commission, the Windham Regional Commission, the Abenaki Nation of Missisquoi and the Elnu Abenaki Tribe, and the New England Coalition on Nuclear Pollution (NEC). The parties have submitted an MOU to the PUC based on the settlement agreement that reflects: (1) increased financial assurances beyond those included in the original proposal filed by Entergy and NorthStar with the PUC in December 2016 and (2) the establishment of site restoration standards to which NorthStar will adhere as it completes the decommissioning of the site. 

 Vermont Yankee

Vermont Yankee

Under Entergy’s original schedule, as outlined in its Post Shutdown Decommissioning Activities Report filed with the NRC in December 2014, Entergy expected to initiate decontamination and dismantlement of the Vermont Yankee site in 2068, with projected completion of both decommissioning and site restoration by 2075.  Under the proposed transaction, NorthStar has committed to initiate decontamination and dismantlement by 2021 (and potentially as early as 2019) and to complete decommissioning and restoration of the Vermont Yankee site, with the exception of the ISFSI and other structures identified above, by 2030 (and potentially as early as 2026).  (Entergy Press Release, 3/2/2018)